Stakeholder Power/Interest Grid
A 2x2 classification of stakeholders by their authority over the project and their interest in its outcome, producing a differentiated engagement strategy for each quadrant.
- 1
- 2
- 3
- 4
- 5
- 6
Field 01
PMI credentials from associate to portfolio level — the global standard for delivery, risk, scheduling and programme leadership.
Exam blueprints, week-by-week study plans, formula calculators and frameworks — plus the real cost of every certification in this field.
8 of 8 certifications
PMI
Total cost
$525 – $1,200
PMI
Total cost
$1,000 – $2,300
PMI
Total cost
$1,200 – $3,200
PMI
Total cost
$1,300 – $2,500
PMI
Total cost
$1,400 – $2,700
PMI
Total cost
$1,400 – $2,700
PMI
Total cost
$2,800 – $5,500
PMI
Total cost
$3,300 – $6,000
Run the numbers before you commit to a credential.
The models examiners expect you to apply, step by step.
A 2x2 classification of stakeholders by their authority over the project and their interest in its outcome, producing a differentiated engagement strategy for each quadrant.
A scoring grid that ranks identified risks by likelihood and consequence so that limited response effort goes to the risks that actually threaten objectives.
A deliverable-oriented hierarchical decomposition of the total project scope into work packages small enough to estimate, assign and control.
A network analysis technique that computes the longest path of dependent activities to determine the shortest possible project duration and the float available on every other path.
Every formula with variables, interpretation thresholds and a worked example.
CPI = EV / AC
Worked example
An office fit-out has a $400,000 budget. At the end of month 3 the team has completed 45% of the planned scope and spent $210,000.
CPI = 180,000 / 210,000 = 0.857
The project earns only 86 cents of value per dollar spent — roughly 14% cost overrun if the trend holds.
Try: An office fit-out has a $400,000 budget.
SPI = EV / PV
Worked example
A software rollout planned $250,000 of work by week 10 but has earned $220,000 of value.
SPI = 220,000 / 250,000 = 0.88
The team is delivering at 88% of planned pace — about 1.2 weeks behind after 10 weeks.
Try: A software rollout planned $250,000 of work by week 10 but has earned $220,000 of value.
CV = EV - AC
Worked example
Same office fit-out: EV $180,000 against AC $210,000.
CV = 180,000 - 210,000 = -30,000
The project is $30,000 over budget for the work completed so far.
Try: Same office fit-out: EV $180,000 against AC $210,000.
SV = EV - PV
Worked example
Software rollout: EV $220,000 against PV $250,000 at week 10.
SV = 220,000 - 250,000 = -30,000
$30,000 worth of planned work has not been delivered yet.
Try: Software rollout: EV $220,000 against PV $250,000 at week 10.
EAC = BAC / CPI
Worked example
Office fit-out with BAC $400,000 running at CPI 0.86.
EAC = 400,000 / 0.857 = 466,744
Expect roughly $67,000 of overrun unless cost efficiency improves.
Try: Office fit-out with BAC $400,000 running at CPI 0.
ETC = EAC - AC
Worked example
Office fit-out: EAC $466,700 with $210,000 already spent.
ETC = 466,700 - 210,000 = 256,700
$256,700 more is needed, versus $190,000 of budget remaining — a $66,700 funding gap.
Try: Office fit-out: EAC $466,700 with $210,000 already spent.
VAC = BAC - EAC
Worked example
Office fit-out: BAC $400,000, EAC $466,700.
VAC = 400,000 - 466,700 = -66,700
Raise a change request for roughly $67,000 or cut scope now.
Try: Office fit-out: BAC $400,000, EAC $466,700.
TCPI = (BAC - EV) / (BAC - AC)
Worked example
Office fit-out: BAC $400,000, EV $180,000, AC $210,000.
TCPI = (400,000 - 180,000) / (400,000 - 210,000) = 220,000 / 190,000 = 1.158
The team must work 16% more cost-efficiently than planned for the rest of the project — unlikely at CPI 0.86.
Try: Office fit-out: BAC $400,000, EV $180,000, AC $210,000.
E = (O + 4M + P) / 6
Worked example
A data-migration task is estimated at 8 days optimistic, 12 days most likely, 26 days pessimistic.
E = (8 + 4x12 + 26) / 6 = 82 / 6 = 13.67
Plan 14 days, not 12 — the long tail adds nearly two days of expected duration.
Try: A data-migration task is estimated at 8 days optimistic, 12 days most likely, 26 days pessimistic.
SD = (P - O) / 6
Worked example
Same data-migration task: O = 8 days, P = 26 days, E = 13.7 days.
SD = (26 - 8) / 6 = 3.0
There is ~95% confidence the task lands between 7.7 and 19.7 days (E ± 2 SD) — commit to 20 days externally.
Try: Same data-migration task: O = 8 days, P = 26 days, E = 13.
Channels = n(n - 1) / 2
Worked example
A steering group has 9 members and two new directors join.
Before: 9x8/2 = 36. After: 11x10/2 = 55.
Adding two people adds 19 communication paths — formalise the reporting structure.
Try: A steering group has 9 members and two new directors join.
TF = LS - ES = LF - EF
Worked example
Activity D on a non-critical path: ES day 12, EF day 17, LS day 19, LF day 24.
TF = 19 - 12 = 7 (and 24 - 17 = 7)
Activity D can slip up to 7 days before it becomes critical — a safe place to borrow resources from.
Try: Activity D on a non-critical path: ES day 12, EF day 17, LS day 19, LF day 24.